Sustainable intensification of cereal-based farming systems in Eastern and Southern Africa

Project Inception Workshop

6-9 February 2012, Dar es Salaam, Tanzania


MANAGING THE OVERALL PROGRAM






1. Program level has:


Program M&E
- own process [ifpri]


Program comms and faciliation
- ilri to lead
- coordinated and consistent approach/strategy
- drawing in comms expertise from partners
- single web presence
- collab space, facilititation
- email, beyond the web
- need an approach/strategy by April 1
- needs a budget / who the people


Program research approach
- own process


Program coordination
- program coordination team
- advises USAID

- coordination and integration / not supervisory
- ensures good comms and learning
- standard setting / guidelines
- convene/sponsor an annual program-wide learning/coordination meeting
- convene/sponsor/approve the research approach design process
- meets annual face to face / plus virtual at least quarterly
- composition: project coordinators + ifpri + usaid + comms/facilitation role + any other key role
- reporting? project - > usaid ; cc this group?
- comms group needs to act as the secretary


2 other issues

ifpri reporting? also into the regional project reports

can we change the reporting to 6-monthly? annual report [+ 6-monthly update]

decide on a program-wide event/meeting/coordination and learning space, before May 31, 2012


USAID to compose a 'signal letter'; indicating next steps, timelines etc



Project workplans will set out the process for 'early wins' ; each early win would have a little workplan